2025 Wharf End Interim Repair Project

Wharf-End-2024-Repair-Project.png

2025 Wharf End Interim Repair Project

Wharf-End-2024-Repair-Project.png

Santa Cruz Wharf End Interim Repair Project

Prior to December 23, 2024 the City was engaged in the 2024 Wharf Repair Project entailing the replacement and repairs of piles and associated structural elements damaged during prior winter storms. The Project Area extended from Bents 167 through 183.

The Santa Cruz Wharf experienced a powerful high surf event on December 23, 2024 leading to a partial collapse of the Santa Cruz Wharf affecting Bents 167 through 183.

Bents 167 through 171 remained standing after the December 23, 2024 event, but suffered varying degrees of damage including missing piles and damage to associated pile caps, stringers and decking.

The City intends to conduct the Santa Cruz Wharf End Interim Repair Project at Bents 167 through 171 to restore that area to its pre-collapse condition and footprint. An existing sea lion viewing hole at this location will be retained. No additional work or improvements to this area are contemplated at this time.

Repairs are expected to begin on or about October/November 2025 and are expected to be completed by February 2026.

 

 SC Wharf End Interim Repair Project Image

Documents

Wharf End Interim Repair Project Drawings

Wharf End Interim Repair Project Specifications

 

Location

59 Municipal Wharf,  95060  View Map

Google Map